N. Salem Water Rehabilitation Project
Project Timeline: July 26, 2021 - (approximately) August 30, 2021
Project Overview
Beginning July 26th, partial road closures will be necessary to repair a water main through downtown Apex. Work will be done on N. Salem Street from NC55 to Chatham Street, and from Center Street to Hunter Street. Expect delays in this area of town from 9am-5pm daily, for about 5 weeks.
In order to minimize disturbance to local residents and businesses, the Town will rehabilitate the existing water line instead of a traditional dig-and-replace project. By doing a rehabilitation, a small (5’x5’) access point every 500’ along the project route is needed and therefore, will result in temporary/partial lane closures, maintaining at least 1 lane of traffic open at all times. Whenever possible, 2 full lanes will be open.
Water Service
Water customers around the area may experience a brief water outage as water is temporarily switched to a bypass water line, and those affected will be notified in advance. Once construction is complete, water service will be switched back to the new, rehabilitated water line and the bypass pipe will be removed. This switch back will again cause a brief outage, and all customers will be notified in advance.
Parking/Driveway Access
While we can’t guarantee that your driveway will never be blocked, the goal is to set up all equipment and access points away from driveways. If, a driveway is temporarily blocked, customers will be notified so that alternate parking and access accommodations can be made.
If you have any questions, please contact Jamie Gregg, Utilities Engineering Manager at 919-249-3324 or james.gregg@apexnc.org.
Laura Duncan Road Pedestrian Improvements
Project Timeline: August 2, 2021 - (approximately) September 30, 2021
Project Overview
Beginning Monday, August 2nd, partial road closures will be necessary to create pedestrian improvements on Laura Duncan Road from Old Apex Road to Chardstone Ct. Construction includes milling, paving, and pavement markings. The contractor will maintain traffic during construction with lane closures and flagging as needed. Lane closures are restricted Monday - Friday between 6:00 am - 9:00 am, and 4:00 pm - 7:00 pm.
If you have any questions, please contact Adam Stephenson, Transportation Engineering Manager at adam.stephenson@apexnc.org
Kelly & Apex Barbecue Sidewalk
Project Timeline: August 2, 2021 - (approximately) March 22, 2022
Project Overview
A concrete sidewalk will be constructed on the east side of Kelly Road from Beaver Trail to Apex Barbecue Road. An asphalt multi-use path will be constructed on the south side of Apex Barbecue Road from Kelly Road to Scotts Ridge Elementary School, including modifications to the bridge over NC 540 to add a concrete barrier between the pedestrian path and the roadway.
If you have any questions, please contact Adam Stephenson, Transportation Engineering Manager at adam.stephenson@apexnc.org
East Williams Street (NC 55) Sidewalk
Project Timeline: August 2, 2021 - (approximately) March 22, 2022
Project Overview
A concrete sidewalk will be constructed on the east side of NC 55 (East Williams Street) and along Bobbit Road from Sunset Lake Road northward, providing connections to existing sidewalk along NC 55 and Sunset Lake Road. The purpose of this project is to provide a pedestrian route and improve connectivity in an area with heavy pedestrian use and activity centers.
If you have any questions, please contact Adam Stephenson, Transportation Engineering Manager at adam.stephenson@apexnc.org